Paving Schedule Update

Public Works Department
December 5, 2018

Paving Schedule Update for weeks 11/20 & 11/26

East Coast Construction Start Pavement Date
Reardon Dr Tuesday 11/20/2018 Completed binder course 11/19/18
Arruda Terr Tuesday 11/20/2018 Completed binder course 11/19/18
Stockton Dr Wednesday 11/21/2018 Completed binder course 11/21/18
Barton Ln Week of 11/26/2018. Prep work Friday 11/30. Paving Saturday 12/1 and continuing week of 12/3. Flyer hand delivered to residences Completed binder course 12/1/18
CB Utility Construction starting week of 11/26/18 Revised: week of 12/3/18
Fenner Ave replace road base In progress
Boulevard replace road base
North Fenner Ave mill binder
Vernon Ave mill binder
Livinston Pl replace road base

 

Citizen Request